Timeline

Fall 2006

  • Complete the design process
  • Release earthwork bid package
  • Analyze mock-up rooms
  • Begin site preparation

Winter 2006/07

  • Release central plant and foundation bid package
  • Begin foundation placement Spring 2007
  • Begin structural framing Summer 2007
  • Release interior and landscape bid package
  • Begin building enclosure, mechanical and electrical construction Summer 2008
  • Begin interiors

Fall 2008 - Summer 2009

  • Begin commissioning
  • Complete interiors
  • Relocate & install technology and equipment

Fall 2009

  • Orient staff
  • Open doors!