Timeline
Fall 2006
Complete the design process
Release earthwork bid package
Analyze mock-up rooms
Begin site preparation
Winter 2006/07
Release central plant and foundation bid package
Begin foundation placement Spring 2007
Begin structural framing Summer 2007
Release interior and landscape bid package
Begin building enclosure, mechanical and electrical construction Summer 2008
Begin interiors
Fall 2008 - Summer 2009
Begin commissioning
Complete interiors
Relocate & install technology and equipment
Fall 2009
Orient staff
Open doors!